APPENDIX C

 

LAND DISTURBANCE PERMIT POLICY
Land Disturbance Permit Policy
Bradley County
, TN

 

 

Table of Contents

1.0 GENERAL

1.1 Purpose/Scope
1.2 Authority

2.0 DEFINITIONS
3.0 PERMITTING PROCEDURES

3.1 Required Signatures
3.2 Exceptions for Land Disturbance Permit
3.3 Responsibility not Waived

3.4 Site Plan and/or Conceptual Grading Plan Requirements

3.5 Plan Submittal, Review, and Approval Process for Land Disturbance Permits

4.0 LAND DISTURBANCE PERMIT FEES
5.0 EROSION & SEDIMENTATION CONTROL

5.1 Control Measures

6.0 RESPONSIBILITY AND ENFORCEMENT OF LAND DISTURBANCE POLICY

6.1 Enforcement Measures

6.2 Responsibility for Utilities - Locations and Service Arrangements

7.0 PROCEDURE FOR APPEAL
8.0 CONTACTS

 

 


Land Disturbance Permit Policy
Bradley County
, TN


1.0 GENERAL

1.1 Purpose/Scope

The intended purpose of this policy is to safeguard life, limb, property and public welfare by regulating clearing, earthwork, excavation, and other land disturbing activity and by requiring temporary and permanent provisions for its control.  It should be used as a planning and engineering implement to facilitate the necessary control of grading and earthwork.

This policy sets forth standards and rules for grading, earthwork or land disturbance and establishes the requirement of a formal permitting procedure. This policy applies to the implementation area within Bradley County and establishes administrative procedures for the issuance of permits and the enforcement thereof, requires the submission of necessary plans (Site or Conceptual Plans) for such work, and the observation & inspection of grading and/or earthwork operations.


1.2 Authority

This policy is developed, implemented, and recognized as a standard practice for Bradley County. The County Commission has approved this Land Disturbance Permit Policy for the management of Land Disturbing Activities within the implementation area. It will be utilized in conjunction with the Subdivision Regulations, Zoning Ordinance, Stormwater Management Policy, and other such codes and texts adopted by Bradley County.

The County Commission has charged the Departments of Stormwater, Engineering and Building Inspections with the administration and enforcement of this policy in regard to the review and approval of grading, excavation, earthwork, and related activities and such management practices as described herein.


2.0 DEFINITIONS

Bedrock - In-place, solid, and undisturbed rock.

 

Best Management Practices (BMPs) – Techniques or practices that reduce the velocity of runoff waters, which can result in the deposition of suspended soil.  BMPs” are physical, structural, and/or managerial practices that, when used singly or in combination, prevent or reduce pollution of water and minimize erosion, that have been approved by Bradley County, and that have been incorporated by reference into this policy as if fully set out therein.

 

 Building Lot Land Disturbance Permit- A permit allowing or authorizing the initiation of grading, excavation or related earthwork according to County Policies, Procedures, Ordinances or adopted codes or referenced texts for disturbance of any lot or parcel on which a building or structure will be placed.


Clearing - The removal from land of trees, shrubs, grass, and/or other varied ground cover and vegetation useful for windbreaks, water retention, and the maintenance of topsoil. Any activity that removes the vegetative surface cover.


Compaction - The densification of materials by mechanical means.


Cut - See excavation.


Earth Material - Any rock and/or natural soil exclusive of any decomposable matter.


Earthwork - Excavation, fill and back fill, compaction, and grading.


Erosion - The wearing away of the ground surface as a result of movement of wind, water, and/or ice.


Excavation - The mechanical removal of earth material.


Fill or Backfill - A deposit of earth by artificial means.


Finish or Final Grade - The grade of the subject site, which conforms to the permitted plan.


Grade - The vertical location of the ground surface to a predetermined elevation datum. The excavation or fill of material, including the resulting conditions thereof.


Grading - The operation of raising or lowering the ground surface to a predetermined grade.

 

Hot Spot – An area where land use or activities generate or have the potential to generate highly contaminated runoff, with concentrations of pollutants n excess of those typically found in stormwater.

 

Impaired Waters – Any segment of surface waters that has been identified by the Environmental Protection Agency as failing to support classified uses. A watercourse delineated by the Tennessee Department of Environment and Conservation which is listed on the “303d” list as degraded with respect to classified uses, including but not limited to recreation, drinking water, agricultural, irrigation, etc.

 

Land Disturbance – Any activity on property that results in a change or alteration in the existing ground cover (both vegetative and non-vegetative) and/or the existing soil topography. Land disturbing activities include, but are not limited to, development, redevelopment, demolition, construction, reconstruction, clearing, grading, filling, excavation and borrow pits.


Land Disturbance Permit - A permit allowing or authorizing the initiation of grading, excavation, or related earthwork according to County Policies, Procedures, Ordinances or adopted codes in conformity to the approved plan(s).

 

Priority Site – Sites that discharge directly into or immediately upstream of waters the state recognizes as impaired or high quality.


Rough Grade - The stage of construction at which the grade approximately conforms to the permitted plan.


Sediment - Solid material, both material and organic, that is in suspension, is being transported, or has been moved from its origin by air, water, gravity, or ice as a product of erosion.


Site – A parcel or portion of a parcel of land or a contiguous combination thereof, where land disturbance or related earthwork is performed as a single unified operation.


Site Plan – A surveyed and engineered graphic representation of a proposed development of a parcel of land describing with reasonable certainty the type and intensity of use thereon.

 

Site Sketch – A graphic representation of a proposed development of a parcel of land describing with reasonable certainty the type and intensity of use thereon.  Applies to single- family residential or multi-family residential less than four units on a parcel up to an acre, or at the discretion of the Bradley County Engineer or Bradley County Building Inspector.

 

Soil - Naturally occurring surface deposits overlying bedrock.


Stockpiling- Temporary storage of erodible material(s) in a common location.


Stormwater - The waters derived from rain falling or snow melting within a tributary drainage basin, flowing over the surface of the ground or collected in a stormwater drainage system.


3.0 PERMITTING PROCEDURES

Unless otherwise stated, no person(s) shall perform any stockpiling, clearing, excavation, or earthwork within the implementation area without first having obtained the appropriate Land Disturbing Permit. 

A separate Land Disturbance Permit will be required for each and every individual building permit or manufactured home permit issued in Bradley County.

A separate Land Disturbance Permit will be required for each phase of a subdivision development.

This section explains the procedure for applying for a Land Disturbance Permit and the process by which the application is reviewed and approved.

This policy is applicable but is not limited to the following activities:

·        Excavating, cutting, filling, grading, draining, or paving or repaving of lots, parcels, or other areas

·        Altering, rerouting, deepening, widening, obstructing, or changing in any way an existing drainage system or feature

·        Development for: residential, commercial, institutional, industrial, utility or other activities

·        Installation of utility extensions and/or replacement either by a utility or a sub contractor

·        Commencing any other development or excavation which may: significantly increase or decrease the rate and/or quantity of surface water runoff; degrade the quality of water; adversely affect any sinkhole, water course, or water body

 

3.1 Signature Requirements

All permit applications and reports must be signed.  Signatures will be accepted only from property owners and/or the general contractors.  If the property owner or general contractor is one of the following, the signatures listed may be accepted:

a)     Corporation:  a president, secretary, treasurer, or vice-president of the corporation or other person who performs similar policy – or decision-making functions for the corporation.

b)     Partnership or sole proprietorship: by general partner or proprietor.

c)      Public facility:  a principal executive officer or the chief executive officer of the agency or a senior executive officer having responsibility for the overall operations of a principal geographic unit of the agency


3.2 Exceptions for Land Disturbance Permits

The following described activities shall not require a Land Disturbance Permit in order to perform clearing, excavation, or related earth work:

·        Any emergency activity that is immediately necessary for the protection of life, property, or natural resources.

·        Septic repair and/or alteration

·        Cemetery graves

·        Sanitary landfill or refuse disposal sites controlled by other regulations

·        Excavations for wells or tunnels (unless performed on the public right-of way)

·        Mining operations controlled by other regulations

·        Temporary stockpiling or storing of materials provided that such operations do not affect adjacent properties and all drainage and erosion control requirements. Temporary stockpiling/storage shall be defined as ninety (90) days or less.

·        Exploratory excavations/drilling under the direction and/or supervision of a licensed soils engineer or geologist

·        Accepted agricultural practices such as plowing, cultivation, construction of agricultural structures, nursery operations, tree cutting, logging operations leaving the stump and root mat intact, and cultivated sod operations

·        Minor landscaping and sprinkler installation


3.3 Responsibility not Waived

The Land Disturbance Permit exceptions listed in Section 3.2 do not relieve the owner, developer, contractor, or other legal representative of the responsibility of installing and properly maintaining the proper erosion/sedimentation control measures or other liability resulting from such activities.


3.4 Site Plan and/or Conceptual Grading Plan Requirements

An approved site sketch (see definition) for disturbance is required for the following activities:

Erecting, enlarging or altering any residential building or structure with less than an acre of land disturbance.

The site sketch shall contain in addition to such basic information as owner name and address, date, tax map and parcel number, the following:

·        The actual shape, location, and dimensions of the lot to be built upon

·        The shape, size and location of all existing and proposed buildings or other structures

·        The location and approximate dimension of all points of access to a public street or road

·        The location of all driveways and entrances

·        Location of areas subject to flooding (if applicable)

 

An approved site plan (see definition) is required for the following activities:

·        Disturbing an acre of land or more

·        Alter the grade of any land as to change the contours in excess of two (2) feet

·        Construction of any road or streets (public or private), alleys, sidewalks, curbs, gutters, retaining walls, drain or sewer, or off street parking lots

·        Changing or diverting the flow of stormwater or natural water courses

If the site plan is inadequate in detail for stormwater management, a separate drainage plan will be required. A licensed civil engineer shall be required to design stormwater systems and plans for sites.

The site plan shall contain, as a minimum, the following items or information. (In addition to basic information such as owner name and address, date, scale, north indication, tax map and parcel number, and etc.).

·        Total land area

·        Existing and proposed topography of existing land and impervious areas shown in five (5) foot intervals (two (2) foot intervals may be required)

·        Elevations of all existing and proposed streets, alleys, utilities, sanitary and stormwater sewers, and existing buildings and structures

·        All existing and proposed impervious areas

·        Natural or artificial watercourses

·        Limits of flood plains (if applicable)

·        Existing and proposed slopes, terraces, or retaining walls

·        All existing and proposed stormwater drainage structures or features

·        All stormwater structures/features immediately upstream and downstream of the site

·        Erosion and siltation control plans

·        Drainage calculations when required

·        Drainage easements when required

If the proposed land disturbance is for purposes of other than actual building construction, a Conceptual Grading Plan may be submitted. This plan will contain all of the above requirements with the exception of any buildings or paving details.

If the proposed land disturbance is for grading only, this should be indicated on the Conceptual Plan. A permit will be issued for "Grading Only". Any future or additional work to include building construction, paving, etc. will require that a Site Plan be submitted and approved and the necessary permits obtained.

 

3.5 Plan Submittal, Review, and Approval Process for Land Disturbance Permits

If Site, Drainage, Conceptual Grading, and Erosion Control Plans for the purpose of obtaining a Land Disturbance Permit are required they shall be submitted to the Engineering and/or Stormwater Department.  They are to be submitted no less than ten (10) working days prior to the intended date to begin site alterations. These plans can be submitted to the Engineering and/or Stormwater Department located at 155 Broad Street, NW.

An Application for a Land Disturbance Permit shall be submitted along with the necessary plans.

The issuance of all other permits is based upon approvals of submitted plans.

All Site, Drainage, Conceptual Grading, and Erosion Control Plans and specifications are to be approved by the County Engineer, or the County Engineer’s designee.

A licensed civil engineer shall be required to design Site, Drainage, Conceptual Grading, and Erosion Control Plans when required by the County Engineer, or the County Engineers’ designee. Such requirements will be based upon the complexity of the conditions, the adjacent properties, and the site itself.

If an applicant determines that his/her plan has been unjustly disapproved or that staff has made requests that are considered above and beyond this policy, he/she may appeal the decision to the Stormwater Administrative Board appointed by the County Commission.

Once the application for a Land Disturbance Permit has been submitted, along with the plans (if required) and the necessary fees, the application will be reviewed by the Engineering and Stormwater Department and upon approval the appropriate permit will be issued.

 The necessary fees can be paid and the permit issued at the Department of Planning, Engineering, Stormwater and Building Inspections located at 155 Broad Street, NW Cleveland, TN 37311.

 The Land Disturbance Permit is valid for a period of one (1) year from the date of issue. Extensions will be considered based on the circumstances. Every Land Disturbance Permit shall expire and become null and void if substantial work authorized by such permit has not commenced within one hundred eighty (180) calendar days of issuance.

The Land Disturbance Permit and copies of the approved drawings are to be present on site at all times when work is underway. The County’s representative may ask to see these at any time.

A Land Disturbance Permit can be suspended or revoked for violation of this or other related policies, procedure, or County Ordinances or adopted codes. A Stop Work Order may be issued if work continues after the Land Disturbance Permit has been revoked. Further action can and will be taken if necessary to insure compliance with this policy.

 

 

 


4.0 LAND DISTURBANCE PERMIT FEES

The fee for the Land Disturbance Permit is intended to assist Bradley County in recovering some of the expenses associated with the permitting process. These costs consist primarily of administration, inspection, and enforcement activities and shall be approved and set by the County Commission.

The fee schedule for Land Disturbance Permits is as follows:

Application fee $50.00. (Non-refundable)  This fee will be applied toward the permit issued.

- Building lot – Residential or commercial

1 (one) lot up to or one acre                                                                         $50.00     

Each additional acre disturbed as per site sketch or site plan          $25.00

 

- Subdivision developments – Road and utility construction, stormwater management related items

            Actual acreage disturbed as per approved site plans                       $50.00 per acre

 

5.0 EROSION & SEDIMENTATION CONTROL

Developers and/or property owners shall use appropriate erosion and sedimentation control measures to ensure that erosion, or adverse conditions caused by erosion or sedimentation, is eliminated or held to an acceptable minimum and does not cross to an adjoining property, R.O.W., street, or stream. All erosion and sedimentation control measures shall conform to the Storm Water Policy adopted by Bradley County and reference publications. 

The County Engineer shall require that a separate, detailed erosion and sedimentation control plan be submitted that complies with Section 3 of the Stormwater Management Policy and any other parts as applicable.

All control measures will be approved in the field by the appropriate staff, typically the Stormwater Inspector, Building Inspector, the County Engineer or his/her designee, and maintained by the developer, builder or property owner.


5.1 Control Measures

The following control measures should be used as a minimum for erosion control.  Control measures should implement Best Management Practices (BMPs) referenced in Bradley County’s Storm Water Policy. 

The smallest practical area of land should be exposed at any one time during development. Best Management Practices as referenced by the Bradley County Storm Water Policy should be used to protect exposed areas.

Perimeter erosion and sediment control measures must be in place and functional before any land disturbance activity begins.

Sites shall contain a temporary stone construction entrance.  The stone shall be ¾  - 3 ½ inch in diameter and shall be kept clean by adding stone if needed.  The depth shall be a minimum of 6 inches with a width of 20 feet and minimum length of 50 feet or as per approved site sketch.  The property owner or his/her developer or contractor shall maintain this construction entrance throughout the construction process.

Sediment that has escaped the construction site and has collected in the street or drainage structures must immediately be physically removed.

Water Quality Buffer Zones with Vegetative buffers or other protection must be provided along streams, rivers, lakes and ponds to avoid erosion of banks and must comply with the Water Quality Buffer Zone Policy.

Stabilization measures must be performed within seven (7) days in portions of the site where construction activities have temporarily or permanently ceased, and within fifteen (15) days after final grading.

Excavated topsoil to be reused must be stockpiled and encircled with properly installed silt fencing.

Temporary furrows, terraces, sediment or debris basins should be installed to prevent washing and erosion during construction.

Building and waste materials, and non-storm water discharges, such as concrete, paint wash water, or machinery leakage or spillage must be managed to prevent them from entering the stormwater system, ground water or nearby water body.

Erosion prevention and sediment controls must be inspected before a rain event, weekly and 24 hours after 0.50” rain event.  The permitee or general contractor shall maintain record of such checks and repairs.  These records must be kept on-site or in the office of the responsible person and available for review at any time by County staff.  You may use the Monthly Inspection Report and Certification Form for Bradley County.  Projects permitted under the State NPDES permit program must also follow its requirements.  Use of that inspection form is permitted instead of the Bradley County Monthly Inspection and Certification form. These forms should be submitted to the Bradley County Engineering and Stormwater Department on a monthly basis.

Best Management Practices (BMPs) must be inspected by a person who has received training and is certified by the Tennessee Department of Environment and Conservation to inspect and maintain erosion and sediment control practices.

6.0 RESPONSIBILITY and ENFORCEMENT of POLICY

This policy is adopted by the County Commission of Bradley County.

Inspection and enforcement of the conditions described in this policy are the responsibility of, but not limited to, the Bradley County Engineer, or his/her designee, the Bradley County Stormwater Department, the Bradley County Building Inspectors Office, or other person(s) as designated by the County Commission.

Any stockpiling, clearing, earthwork, excavation, and other land disturbing activity not meeting the requirements of this policy will be stopped at the direction of the Bradley County Engineer/Stormwater Administrator, or his/her designee, the Bradley County Building Inspector, his/her designee, or the County Mayor, or his/her designee. Such work may not resume until such time that all provisions are adequately met.

Intentional or continued violation of this policy is considered a civil penalty under Section 10 of the Stormwater Management Policy and is punishable according to the following guidelines:

 

 

 

6.1            ENFORCEMENT MEASURES 

Work Without a Land Disturbance Permit

First Offense                                                   Stop Work Order, Notice of Violation Issued

If work continues                                           Administrative fine of not less than $50 and

not more than $5,000  for each day work continues without permit. Each day of violation shall constitute a separate violation. (SWMP Section 10)

Fill sites in residential areas                           In addition to above, the permit fees are automatically

doubled

 

Failure to Install, Maintain or Use Proper Construction Entrance

First Project Offense                                       Written Warning

Second Offense                                   Notice of Violation issued; Suspension of all County

inspections until violations corrected                                                 

Each Additional Offense                    Administrative fine per each entrance

point per day

Failure to Clean Up Mud                               Bill for three times the cost of County clean up starting on

First Offense

 

Failure to Install, Maintain or Use Proper Structural Erosion or Sediment Control

First Project Offense                           Written Warning

Second Offense                                   Notice of Violation, Suspension of all County Inspections

until Violations corrected, TDEC notification

Each Additional Offense                    In addition to above, Administrative Fine  

Civil Penalty, Land Disturbing Permit Suspension

Failure to Clean Up Discharge           Bill for three times the cost of County clean up starting on

first Offense

 

Non-Storm Water Discharges

First Project Offense                           Notice of Violation, TDEC Notification

Each Additional Offense                    Administrative fine for each violation

 

Failure to Conduct Self Inspections and Maintain Inspection Log Including Updating Erosion Control Plan

First Project Offense                                       Notice of Violation, Required to submit self-inspection

forms monthly

Each additional Offense                     Administrative fine

Failure to submit monthly report

    By 10th of next month                    Administrative fine for each day past 10th

Failure to submit second monthly

    Report by 10th of next month            Administrative fine Civil Penalty

 

NOTE: Each day of violation shall constitute a separate violation and shall be punishable by enforcement measures.


6.2 RESPONSIBILITY for UTILITIES– Locations and Service Arrangements

Neither the Land Disturbance Permit nor the Permit Application address utility services (public or private). The property owner, developer, excavator, and/or contractor are solely responsible for notifying any applicable utility providers of the intent to excavate or commence new construction.

Tennessee State Law requires that the Tennessee One Call service be utilized for all excavations. This number is to be called 72 hours prior to the planned excavation. This number is toll free: 800-351-1111.

The issuance of a Land Disturbance Permit by Bradley County does not in anyway address the provision or availability of utility service to the subject site. The owner, developer, and/or contractor is responsible for making any and all arrangements for requesting utility services in a timely manner. In certain circumstances, utility services may not be readily available to the subject site. In such cases, it will be up to the utility provider and the property owner/requestor to make arrangements for the installation of utility services.


7.0 PROCEDURE FOR APPEAL

If an applicant determines that his/her permit or plan has been unjustly disapproved or that County staff has made requests that are considered above and beyond policy, he/she may appeal the decision to the Stormwater Administrative Board appointed by the County Commission. (Reference Bradley County Stormwater Management Policy adopted by Bradley County.)

This appeal should be in writing, addressed to the Stormwater Administrative Board c/o Bradley County Engineer at 155 Broad Street, NW, Cleveland, TN 37311.  Upon receipt of an appeal a hearing time, date and place will be set and all parties will be notified.

8.0 CONTACTS

Bradley County Engineering and Stormwater Department

155 Broad Street, NW Cleveland, TN 37311

(423) 728-7107

Sandra Knight. County Engineer

 

Bradley County Stormwater Department

155 Broad Street, NW Cleveland, TN 37311

(423) 728-7102

Heath Owens, Stormwater Inspector

 

Bradley County Building Inspectors Office

155 Broad Street, NW Cleveland, TN 37311

(423) 728-7106

Tina Rice, Building Inspector

Don Wyatt, Building Inspector